20 Jan, 2011 By: Phillip ZimmermanCAD Clinic Civil 3D Tutorial: Learn the ins and outs of the formula file, the last of the three files that create a master pay items list.
Editor's Note: This tutorial courtesy of Imaginit.
In my previous article, I reviewed the pay item definition process and the files necessary to implement a master pay item list. In this month's continuation, I will review the formula file and its purpose.
The formula file's use depends on the units set for a pay item. For example, a corridor's Pave1 area is in square feet, but in the pay item file the units are square yards. A pay item report for Pave1 will be in the pay item area units, not the corridor's square feet. If Pave1's assigned pay item unit type is a weight unit type, the pay item report is Pave1's actual area — or, in this case, Pave1's square feet. In either case, you need a formula to calculate a volume.
Pay Item Units
When creating a corridor, the pavement unit type is square feet. As mentioned above, if a pavement material's pay item's unit is square yards, the report will be in square yards. When producing a pay item report, the report's pavement units are in the pay item's units, not the corridor's actual area units. If Pave1's pay item unit is a weight type, the pay item report will be the corridor's actual units, or square feet.
It is very important to be aware of a pay item's unit type, because the unit type affects what value a report produces. In some cases the report's values reflect a conversion of the item's actual units. If the actual and the report unit types are areas, the pay item report contains an amount in pay item units. If the actual units are area and the pay item units are weight, the pay item report contains the actual units. Therefore, if Pave1 pay item's unit is square yards, the pay item report contains Pave1's area as square yards. Or, if Pave1 pay item's unit is ton, the pay item report contains Pave1's square footage. A pay item's unit type determines what values you need to have in a formula to calculate the correct amount.
The Formula File
The formula file is the last of three files that create a master pay items list. This file is optional and does not need to be implemented to use pay item entries. What, then, is the purpose of the formula file? When working with pipes or structures, the interest is in the count or length values. The pay items reports calculate these unit values without a formula.
When working with other materials — for example, roadway materials — the materials need estimated volume or weight values. In a drawing, these materials or pay items are represented by areas and their initial values may come from a corridor and are in square feet or yards, never weights. The formula file converts the area values to weight and/or volume values.
In a code set style, the assignment of a pay item to a link defines only the width of the material in the assembly. In any assembly, the link's width is the sum of its right and/or left sides. The pay item report uses the pay item's units, not the corridor's square feet values, to produce a report value. For example, if Pave2 is a binder and its pay item unit area is square yards, the Pave2 pay item report will be in square yards even though the corridor area of Pave2 is square feet. If Pave2 pay item's unit is tons, the pay item report contains Pave2's square foot area.
It is necessary to create a formula that calculates the tonnage from Pave2's area unit value. If the pay item unit is square yards, a formula would multiply the area by the material depth to calculate the cubic yards. The depth of material is in yards; 2 inches of binder is 2/36 inches, or 0.05555555 of a yard. The pay item unit value is enclosed in braces, and parentheses encapsulate the order of calculations.
The resulting formula segment would be: ({Item Area} * 0.0555555)
The second formula segment calculates the number of pounds in a cubic yard; e.g., 3,000 pounds per cubic yard. This formula segment would be: * 3000.00. The last formula segment calculates the number of tons of material — the number of pounds divided by a ton. Again, parentheses encapsulate the order of calculations; pounds per cubic yard, then the number of tons.
The resulting formula would be: (({Item Area} * 0.055555550) * 3000.00) / 2000
For the area of 5,000 square yards, the cubic yards would be 277.775. The weight of this volume is 833325 pounds. The tonnage value would be 416.6625. The pay item report will list 416.6625 as the tonnage for the material.
1 2

|
|
AutoCAD Tips!
Autodesk Technical Evangelist Lynn Allen guides you through a different AutoCAD feature in every edition of her popular "Circles and Lines" tutorial series. For even more AutoCAD how-to, check out Lynn's quick tips in the Cadalyst Video Gallery. Subscribe to Cadalyst's Tips & Tricks Tuesdays free e-newsletter and we'll notify you every time a new video tip is available. All exclusively from Cadalyst! |
|